June 26, 2019

Almost there!

We are nearing completion and its all hands on deck to make the final push. Exterior scaffolding is starting to come down, the painters are in […]
April 17, 2019

Roof on, time for that roof shout!

Progress has been steady over the past few weeks, the sunny Autumn days certainly help. Roof has been installed and windows measured, lets hope this weather […]
March 29, 2019

Taking shape

Hi there, latest drone pics attached. Structural steel all in place and the large timber rafters are being installed Full scaffolding is required at this stage […]
March 19, 2019

Structural Steel Onsite

After a small delay we finally lifted the structural steel on to site today and erection will happen over the coming days. Also managed to get […]
February 13, 2019

Floor completed

Hi Everyone….as you can see from the drone pics the floor has been completed and the deck posts are about to be concreted. The structural steel […]
January 30, 2019

Foundations

The foundation piles have been drilled and are now ready for concrete.   Posts braced and ready for concrete
January 30, 2019

Tree removal and site scrape….

Trees removed and a site tidy, ready for the foundation piles to be dug. Look out Mr volley wall….your next!
December 11, 2018

Milford Tennis Club

Building will start Monday Jan 14th. All the courts will remain in use but access to the Bottom Courts will be via the side gate. The construction area will be fenced off, but children must be supervised at all times and everyone must keep clear of the site. Our existing clubhouse will remain until the new clubhouse is ready for use, at which time the old clubhouse will be demolished and the land planted.